Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team's attention…
The correct answer is A. Incorporate it into the risk register and perform a thorough analysis. See the full explanation below for the reasoning.
Question
Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team's attention. What should be done with the identified potential risk?
Options
- AIncorporate it into the risk register and perform a thorough analysis
- BMitigate the risk before it is incorporated into the risk management plan
- CDocument the risk in the program transition plan and identify it as a potential issue
- DDocument it m the issue log and immediately notify the steering committee
How the community answered
(33 responses)- A85% (28)
- B3% (1)
- C3% (1)
- D9% (3)