nerdexam
BICSI

RCDD-002 · Question #303

Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team's attention…

The correct answer is A. Incorporate it into the risk register and perform a thorough analysis. See the full explanation below for the reasoning.

Question

Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team's attention. What should be done with the identified potential risk?

Options

  • AIncorporate it into the risk register and perform a thorough analysis
  • BMitigate the risk before it is incorporated into the risk management plan
  • CDocument the risk in the program transition plan and identify it as a potential issue
  • DDocument it m the issue log and immediately notify the steering committee

How the community answered

(33 responses)
  • A
    85% (28)
  • B
    3% (1)
  • C
    3% (1)
  • D
    9% (3)

Community Discussion

No community discussion yet for this question.

Full RCDD-002 Practice