RCDD-002 · Question #103

Status information, including program and component status, cost information, risk analysis and other relevant information, is provided in which of the following?

The correct answer is A. Program performance report. Program performance reports (A) are the designated output for consolidating status information - program and component status, cost data, risk analysis, forecasts, and other relevant metrics - into a single document distributed to stakeholders. This is a core concept in program…

ICT Design Fundamentals and Project Management

Question

Status information, including program and component status, cost information, risk analysis and other relevant information, is provided in which of the following?

Options

  • AProgram performance report
  • BCommunications management plan
  • CCommunications log updates
  • DInformation gathering and retrieval system

How the community answered

(37 responses)
  • A
    73% (27)
  • B
    5% (2)
  • C
    8% (3)
  • D
    14% (5)

Explanation

Program performance reports (A) are the designated output for consolidating status information - program and component status, cost data, risk analysis, forecasts, and other relevant metrics - into a single document distributed to stakeholders. This is a core concept in program management frameworks like PMI's Standard for Program Management.

Why the distractors are wrong:

  • B (Communications management plan) describes how communications will happen (who gets what, when, and how) - it's a planning document, not a status report.
  • C (Communications log updates) is a record of communications that have occurred, not a vehicle for delivering status content.
  • D (Information gathering and retrieval system) is a tool or system used to store and access information, not a report that delivers it to stakeholders.

Memory tip: Think of the word "report" - when you need to report performance (status, cost, risk), you use a performance report. Plans plan, logs log, systems store - only reports report.

Topics

#Program performance report#Project status information#Cost and risk reporting#Project management documentation