PSPO-I · Question #85
Which outcome is expected as a Scrum Team matures? (choose the best answer)
The correct answer is B. They will improve their Definition of Done to include more stringent criteria. A mature Scrum Team is expected to continuously improve their quality standards and deliver potentially releasable Increments of value that meet the Definition of Done12. The Definition of Done is a shared understanding of what it means to complete a Product Backlog item, and…
Question
Which outcome is expected as a Scrum Team matures? (choose the best answer)
Options
- AThe Sprint Retrospectives will grow to be longer than 4 hours.
- BThey will improve their Definition of Done to include more stringent criteria.
- CA Scrum Master is no longer needed since they are a mature team now.
- DThere will be no need for a timeboxed Sprint.
- ESprint Reviews will no longer be needed.
How the community answered
(25 responses)- A4% (1)
- B76% (19)
- C12% (3)
- D4% (1)
- E4% (1)
Explanation
A mature Scrum Team is expected to continuously improve their quality standards and deliver potentially releasable Increments of value that meet the Definition of Done12. The Definition of Done is a shared understanding of what it means to complete a Product Backlog item, and it may vary from one Scrum Team to another3. As the Scrum Team matures, they may expand their Definition of Done to include more rigorous criteria, such as higher levels of testing, documentation, performance, security, usability, etc . This way, they ensure that their product Increment is always ready for release and meets the expectations of the stakeholders and customers12.