PSPO-I · Question #142

When must the Product Owner participate in the Daily Scrum? (choose the best answer)

The correct answer is B. When the Product Owner is actively working on items on the Sprint Backlog. Option B is correct because the Daily Scrum is a working session for the Developers, but the Product Owner is obligated to attend only when they are actively doing Sprint Backlog work themselves - in that case, they attend as a contributing team member, not in their PO…

Applying Scrum

Question

When must the Product Owner participate in the Daily Scrum? (choose the best answer)

Options

  • AWhen the Scrum Master asks the Product Owner to attend.
  • BWhen the Product Owner is actively working on items on the Sprint Backlog;
  • CWhen there are impediments to discuss.
  • DWhen the Product Owner needs to represent the stakeholders' point of view to the

How the community answered

(26 responses)
  • A
    12% (3)
  • B
    81% (21)
  • C
    4% (1)
  • D
    4% (1)

Explanation

Option B is correct because the Daily Scrum is a working session for the Developers, but the Product Owner is obligated to attend only when they are actively doing Sprint Backlog work themselves - in that case, they attend as a contributing team member, not in their PO capacity.

Why the distractors are wrong:

  • A - The Scrum Master has no authority to mandate PO attendance; the Scrum Guide does not give the SM that power.
  • C - Impediments are handled by the Scrum Master and Developers during or after the Daily Scrum; the PO's presence is not required for this.
  • D - The Daily Scrum is not a stakeholder communication event; the PO represents stakeholder interests through the Sprint Goal and Product Backlog, not by attending Daily Scrums.

Memory tip: Think of the Daily Scrum as "Developers only by default." The PO earns their seat the same way anyone does - by doing the work. If they're pulling Sprint Backlog items, they join; otherwise, attending is optional, not mandatory.

Topics

#Daily Scrum#Product Owner participation#Sprint Backlog