Question

Developers are self-managing, which of the following do they manage? (choose the best answer)

Options

  • AProduct Backlog ordering.
  • BWhen to release, based on its progress.
  • CSprint Backlog.
  • DStakeholders for the Sprint Review.
  • ESprint length.