True or False: Cross-functional teams are optimized to work on one component or layer of a system only.

The correct answer is B. False. Cross-functional teams are not optimized to work on one component or layer of a system only. This is Cross-functional teams are teams that have all the skills and competencies needed to accomplish the work without depending on others who are not part of the team…

Applying Scrum

Question

True or False: Cross-functional teams are optimized to work on one component or layer of a system only.

Options

  • ATrue
  • BFalse

How the community answered

(54 responses)
  • A
    6% (3)
  • B
    94% (51)

Explanation

Cross-functional teams are not optimized to work on one component or layer of a system only. This is Cross-functional teams are teams that have all the skills and competencies needed to accomplish the work without depending on others who are not part of the team. Cross-functional teams are able to deliver value across the entire product, rather than focusing on a specific component or layer. They can work on any aspect of the product that is needed to achieve the Sprint Goal and the Product Goal. Cross-functional teams are more agile, collaborative, and creative than teams that are specialized or siloed. They can reduce dependencies, handoffs, and delays, and increase feedback, learning, and [Scrum Guide], page 7, section "Developers" [Scrum Guide], page 10, section "Product Goal" [Scrum Guide], page 7, section "The Scrum Team"