PSPO-I · Question #84

PSPO-I Question #84: Real Exam Question with Answer & Explanation

Sign in or unlock PSPO-I to reveal the answer and full explanation for question #84. The question stem and answer options stay visible for context.

Question

Which two things are appropriate for a Scrum Master to do, if the Scrum Team does not have the tools and environment to completely finish each selected Product Backlog item? (choose the best two answers)

Exhibit

PSPO-I question #84 exhibit

Options

  • ACoach the Scrum Team to improve its skills, tools and environment over time and adjust the
  • BRefocus the current Sprint on establishing the Scrum Team's environment instead of delivering an
  • CEncourage the Product Owner to accept partially done Increments until the situation improves.
  • DHave the Scrum Team establish a Definition of Done that is actually possible to achieve given
  • EDeclare the Scrum Team not ready for Scrum. This is not an appropriate action for a Scrum Master,