PSPO-I · Question #164

When should a Sprint Goal be created? (choose the best answer)

The correct answer is D. During Sprint Planning. The Sprint Goal is a short statement that gives the Sprint a purpose, direction, and focus. It is created by the entire Scrum Team during Sprint Planning, based on the Product Owner's draft and the Developers' input. The Sprint Goal is then added to the Sprint Backlog and…

Applying Scrum

Question

When should a Sprint Goal be created? (choose the best answer)

Options

  • AA Sprint Goal is not mandatory in Scrum.
  • BIt should have been created in the previous Sprint during Product Backlog
  • CIt must be established before Sprint Planning in order to begin planning.
  • DDuring Sprint Planning.
  • EAt any time during the Sprint.

How the community answered

(37 responses)
  • A
    8% (3)
  • B
    3% (1)
  • C
    3% (1)
  • D
    86% (32)

Explanation

The Sprint Goal is a short statement that gives the Sprint a purpose, direction, and focus. It is created by the entire Scrum Team during Sprint Planning, based on the Product Owner's draft and the Developers' input. The Sprint Goal is then added to the Sprint Backlog and guides the Developers' work during the Sprint. What is a Sprint Goal? How to Write and Use a Sprint Goal (With 5 Templates)

Topics

#Sprint Goal#Sprint Planning#Sprint Goal creation