nerdexam
Scrum

PSPO-I · Question #165

Which of these may a Scrum Team deliver at the end of a Sprint? (choose the best answer)

The correct answer is D. A valuable, useful Increment that meets the Definition of Done. The Scrum Guide states that "the Increment is the sum of all the Product Backlog items completed during a Sprint and the value of the increments of all previous Sprints". It also states that "at the end of a Sprint, the new Increment must be 'Done', which means it must be in…

Value Management

Question

Which of these may a Scrum Team deliver at the end of a Sprint? (choose the best answer)

Options

  • AFailing unit tests, to identify acceptance tests for the next Sprint.
  • BA single document, if that is what management asked for.
  • CAn Increment of software with minor known bugs in it.
  • DA valuable, useful Increment that meets the Definition of Done.

How the community answered

(61 responses)
  • A
    2% (1)
  • B
    5% (3)
  • C
    7% (4)
  • D
    87% (53)

Explanation

The Scrum Guide states that "the Increment is the sum of all the Product Backlog items completed during a Sprint and the value of the increments of all previous Sprints". It also states that "at the end of a Sprint, the new Increment must be 'Done', which means it must be in useable condition and meet the Scrum Team's definition of 'Done'". Therefore, the Scrum Team must deliver a valuable, useful Increment that meets the Definition of Done at the end of a Sprint. The other options are not acceptable, as they do not meet the criteria of being valuable, useful, or done. The Scrum Guide, section 3.4. Increment Professional Scrum Product Owner I (PSPO I) Learning Path, section 2.1. The Product Owner and the Development Team Professional Scrum Product Owner I (PSPO I) Sample Questions, question 10

Topics

#Increment#Definition of Done#Sprint delivery#value

Community Discussion

No community discussion yet for this question.

Full PSPO-I Practice