PSPO-I · Question #165
Which of these may a Scrum Team deliver at the end of a Sprint? (choose the best answer)
The correct answer is D. A valuable, useful Increment that meets the Definition of Done. The Scrum Guide states that "the Increment is the sum of all the Product Backlog items completed during a Sprint and the value of the increments of all previous Sprints". It also states that "at the end of a Sprint, the new Increment must be 'Done', which means it must be in…
Question
Which of these may a Scrum Team deliver at the end of a Sprint? (choose the best answer)
Options
- AFailing unit tests, to identify acceptance tests for the next Sprint.
- BA single document, if that is what management asked for.
- CAn Increment of software with minor known bugs in it.
- DA valuable, useful Increment that meets the Definition of Done.
How the community answered
(61 responses)- A2% (1)
- B5% (3)
- C7% (4)
- D87% (53)
Explanation
The Scrum Guide states that "the Increment is the sum of all the Product Backlog items completed during a Sprint and the value of the increments of all previous Sprints". It also states that "at the end of a Sprint, the new Increment must be 'Done', which means it must be in useable condition and meet the Scrum Team's definition of 'Done'". Therefore, the Scrum Team must deliver a valuable, useful Increment that meets the Definition of Done at the end of a Sprint. The other options are not acceptable, as they do not meet the criteria of being valuable, useful, or done. The Scrum Guide, section 3.4. Increment Professional Scrum Product Owner I (PSPO I) Learning Path, section 2.1. The Product Owner and the Development Team Professional Scrum Product Owner I (PSPO I) Sample Questions, question 10