nerdexam
Scrum

PSPO-I · Question #160

When does a Developer become accountable for an item in the Sprint Backlog? (choose the best answer)

The correct answer is C. Never. All Developers on the Scrum Team share accountability for items in the Sprint. The Developers on the Scrum Team share accountability for the Sprint Backlog, which is a forecast of the work and the plan to deliver the Sprint Goal12. The Sprint Backlog is dynamic and can be updated by the Developers as more is learned during the Sprint34. The Developers are…

Applying Scrum

Question

When does a Developer become accountable for an item in the Sprint Backlog? (choose the best answer)

Options

  • ADuring the Daily Scrum.
  • BAs soon as a Developer on the Scrum Team can accommodate more work.
  • CNever. All Developers on the Scrum Team share accountability for items in the Sprint
  • DAt Sprint Planning when all of the Sprint Backlog items are split evenly across the

How the community answered

(31 responses)
  • A
    3% (1)
  • C
    94% (29)
  • D
    3% (1)

Explanation

The Developers on the Scrum Team share accountability for the Sprint Backlog, which is a forecast of the work and the plan to deliver the Sprint Goal12. The Sprint Backlog is dynamic and can be updated by the Developers as more is learned during the Sprint34. The Developers are not individually accountable for the items in the Sprint Backlog, nor are they assigned by the Scrum Master or the Product Owner5.

Topics

#Sprint Backlog#shared accountability#Developer responsibility#Scrum Team

Community Discussion

No community discussion yet for this question.

Full PSPO-I Practice