PSPO-I · Question #160
PSPO-I Question #160: Real Exam Question with Answer & Explanation
The correct answer is C. Never. All Developers on the Scrum Team share accountability for items in the Sprint. The Developers on the Scrum Team share accountability for the Sprint Backlog, which is a forecast of the work and the plan to deliver the Sprint Goal12. The Sprint Backlog is dynamic and can be updated by the Developers as more is learned during the Sprint34. The Developers are n
Question
Options
- ADuring the Daily Scrum.
- BAs soon as a Developer on the Scrum Team can accommodate more work.
- CNever. All Developers on the Scrum Team share accountability for items in the Sprint
- DAt Sprint Planning when all of the Sprint Backlog items are split evenly across the
Explanation
The Developers on the Scrum Team share accountability for the Sprint Backlog, which is a forecast of the work and the plan to deliver the Sprint Goal12. The Sprint Backlog is dynamic and can be updated by the Developers as more is learned during the Sprint34. The Developers are not individually accountable for the items in the Sprint Backlog, nor are they assigned by the Scrum Master or the Product Owner5.
Community Discussion
No community discussion yet for this question.