PSPO-I · Question #159

PSPO-I Question #159: Real Exam Question with Answer & Explanation

Sign in or unlock PSPO-I to reveal the answer and full explanation for question #159. The question stem and answer options stay visible for context.

Question

Which of the following are criteria to order Product Backlog items?

Options

  • AThe value of the Product Backlog items.
  • BThe availability of the Scrum Master.
  • CDependencies between Product Backlog items.
  • DTheir relevance to achieving the Product Goal.
  • EThe number of stakeholders who approve of the item.

Unlock PSPO-I to see the answer