nerdexam
Scrum

PSPO-I · Question #158

PSPO-I Question #158: Real Exam Question with Answer & Explanation

The correct answer is A. Remove or change selected Product Backlog items. B. The Developers ensure that the Scrum Team is aware, start the Sprint, and. According to the Scrum Guide1, the Developers are responsible for selecting the amount of work they can do in a Sprint, based on their capacity and past performance2. If they realize that the workload may be greater than their capacity, they can either remove or change some of th

Question

As the Sprint Planning progresses, the Developers realize that the workload may be greater than their capacity to complete the work. Which two are valid actions? (choose the best two answers)

Options

  • ARemove or change selected Product Backlog items.
  • BThe Developers ensure that the Scrum Team is aware, start the Sprint, and
  • CRecruit additional Developers before the work can begin.
  • DCancel the Sprint.
  • EThe Developers work overtime during this Sprint.

Explanation

According to the Scrum Guide1, the Developers are responsible for selecting the amount of work they can do in a Sprint, based on their capacity and past performance2. If they realize that the workload may be greater than their capacity, they can either remove or change some of the selected Product Backlog items, or they can start the Sprint and monitor the progress, making adjustments as needed3. Recruiting additional Developers, canceling the Sprint, or working overtime are not valid actions, as they would disrupt the Scrum values of commitment, focus, and respect

Community Discussion

No community discussion yet for this question.

Full PSPO-I Practice