Steven is a Scrum Master for three Scrum Teams building the same product and working from the same Product Backlog. Management wants to standardize how velocity is calculated across all three teams…

The correct answer is A. There is no direct relationship between velocity and value. D. Velocity is the amount of business functionality that a Scrum Team creates in a Sprint. It is unique. Working software is the primary measure of progress. Scrum is based on empirical process control theory where delivering working software frequently and measuring the impact helps the Product Owner maximize opportunity for the business to deliver value.

Scaling Scrum

Question

Steven is a Scrum Master for three Scrum Teams building the same product and working from the same Product Backlog. Management wants to standardize how velocity is calculated across all three teams in order to identify which teams are high performing and which teams need more support. What would be the best two responses Steven could provide to management? (Choose two.)

Options

  • AThere is no direct relationship between velocity and value.
  • BStandardizing velocity across teams is a good way to understand which teams are producing the
  • CProviding incentives based on velocity can increase the Scrum Team's motivation to produce
  • DVelocity is the amount of business functionality that a Scrum Team creates in a Sprint. It is unique

How the community answered

(41 responses)
  • A
    56% (23)
  • B
    17% (7)
  • C
    27% (11)

Explanation

Working software is the primary measure of progress. Scrum is based on empirical process control theory where delivering working software frequently and measuring the impact helps the Product Owner maximize opportunity for the business to deliver value.