PSM-II · Question #76

What should a Development Team do if it realizes it has selected too much work after starting the Sprint?

The correct answer is B. Work with the Product Owner to remove some work or Product Backlog items as soon as. The Sprint Backlog is a living artifact that evolves and changes as more is learned or discovered.

Applying Scrum

Question

What should a Development Team do if it realizes it has selected too much work after starting the Sprint?

Options

  • AModify the definition of "Done" to ensure all Product Backlog items can be done by the end of the
  • BWork with the Product Owner to remove some work or Product Backlog items as soon as
  • CAdd additional team members to handle the extra work.
  • DContinue working and update the Product Owner at the Sprint Review.

How the community answered

(46 responses)
  • A
    9% (4)
  • B
    85% (39)
  • C
    2% (1)
  • D
    4% (2)

Explanation

The Sprint Backlog is a living artifact that evolves and changes as more is learned or discovered.

Topics

#Sprint scope#overcommitment#Product Owner#Sprint adaptation