PSM-II · Question #52
Which role is responsible for engaging with stakeholders?
The correct answer is E. The Product Owner. In Scrum, the Product Owner is the single point of contact responsible for engaging with stakeholders - gathering their needs, managing expectations, and communicating the product vision to ensure the backlog reflects business value. Why the distractors are wrong: A (Team Lead)…
Question
Which role is responsible for engaging with stakeholders?
Options
- AThe team lead
- BThe business analyst
- CThe project manager
- DThe Development Team
- EThe Product Owner
How the community answered
(47 responses)- B2% (1)
- C4% (2)
- D6% (3)
- E87% (41)
Explanation
In Scrum, the Product Owner is the single point of contact responsible for engaging with stakeholders - gathering their needs, managing expectations, and communicating the product vision to ensure the backlog reflects business value.
Why the distractors are wrong:
- A (Team Lead) - Scrum has no "team lead" role; leadership is shared within the Development Team.
- B (Business Analyst) - Not a defined Scrum role; in Scrum, the PO absorbs this responsibility.
- C (Project Manager) - Also not a Scrum role; project management responsibilities are distributed across all three Scrum roles.
- D (Development Team) - Focuses on delivering the sprint goal, not on stakeholder management.
Memory tip: Think of the Product Owner as the "voice of the customer inside the team" - they face outward toward stakeholders and inward toward the team, making them the natural bridge for all stakeholder engagement.
Topics
Community Discussion
No community discussion yet for this question.