Adding more resources in Scrum will proportionally increase the value delivered.
The correct answer is B. False. When working on complex problems in complex environments, adding more resources (people, money, tools, etc.) cannot guarantee increased value or success.
Applying Scrum
Question
Adding more resources in Scrum will proportionally increase the value delivered.
Options
- ATrue
- BFalse
How the community answered
(16 responses)- A6% (1)
- B94% (15)
Explanation
When working on complex problems in complex environments, adding more resources (people, money, tools, etc.) cannot guarantee increased value or success.
Topics
#team size#value delivery#Scrum principles