PSM-II · Question #35
How should a Scrum Master coordinate the work when more than one Scrum Team is working on one product?
The correct answer is A. Teach them that it's their responsibility to coordinate with the other teams to integrate and create. One of the benefits of self-organized teams is the ability to decide how best to work together to produce a shippable Increment.
Scaling Scrum
Question
How should a Scrum Master coordinate the work when more than one Scrum Team is working on one product?
Options
- ATeach them that it's their responsibility to coordinate with the other teams to integrate and create
- BIdentify and manage the dependencies between Scrum Teams.
- CHave the Product Owner work with the tech leads of each team to parse the Product Backlog and
- DMerge the teams and work from a single Sprint Backlog.
How the community answered
(43 responses)- A79% (34)
- B2% (1)
- C7% (3)
- D12% (5)
Explanation
One of the benefits of self-organized teams is the ability to decide how best to work together to produce a shippable Increment.
Topics
#multiple teams#integration#self-organization#coordination