PSM-II · Question #27

PSM-II Question #27: Real Exam Question with Answer & Explanation

The correct answer is D. The Development Teams pull in work from a shared Product Backlog in agreement with the. During Sprint Planning the number of items selected from the Product Backlog for the Sprint is solely up to the Development Team regardless of the number of Development Teams working from the same Product Backlog. Only the Development Team can assess what it can accomplish over t

Question

On a project where multiple Scrum Teams are working from the same Product Backlog, how should the work be distributed between teams?

Options

  • AThe Scrum Team with the highest capacity will pull items from the Product Backlog first.
  • BEach Scrum Team must have an equal amount of User Stories per Sprint.
  • CThe Product Owner separates the Product Backlog items for each team.
  • DThe Development Teams pull in work from a shared Product Backlog in agreement with the

Explanation

During Sprint Planning the number of items selected from the Product Backlog for the Sprint is solely up to the Development Team regardless of the number of Development Teams working from the same Product Backlog. Only the Development Team can assess what it can accomplish over the upcoming Sprint.