PSM-II · Question #190

Which two statements are the most accurate in regards to scaling Scrum for large projects requiring multiple Scrum Teams? (Choose two.)

The correct answer is A. A person focusing on the Sprint Backlog of a single Scrum Team is often more productive than B. A well-structured Product Backlog can minimize and often eliminate Development Team. A person or team working on a single problem at a time is typically more effective than one that is working on multiple problems congruently as they can fully focus and dedicate their energy to resolving the problem before moving to the next. Having a well-structured Product…

Scaling Scrum

Question

Which two statements are the most accurate in regards to scaling Scrum for large projects requiring multiple Scrum Teams? (Choose two.)

Options

  • AA person focusing on the Sprint Backlog of a single Scrum Team is often more productive than
  • BA well-structured Product Backlog can minimize and often eliminate Development Team
  • CTeam members must work full time on a single Scrum Team.
  • DCustomizing the core Scrum framework is necessary to be successful with Scrum at large scale.

How the community answered

(26 responses)
  • A
    62% (16)
  • C
    12% (3)
  • D
    27% (7)

Explanation

A person or team working on a single problem at a time is typically more effective than one that is working on multiple problems congruently as they can fully focus and dedicate their energy to resolving the problem before moving to the next. Having a well-structured Product Backlog can help minimize dependencies and increase focus for each team. Exam Questions, Study Guides, Practice Tests. Lead the way to help you pass any IT Certification exams, 100% Pass Guaranteed or Full Refund. Especially CiscoVendor: I Exam Name: Professional Scrum Master I 20.051 Nortel, EXIN and so on. Our Slogan: First Test, First Pass. Help you to pass any IT Certification exams at the first try. You can reach us at any of the email addresses listed below. Any problems about IT certification or our products, you could rely upon us, we will give you satisfactory answers in 24 hours.

Topics

#scaling Scrum#multiple teams#Product Backlog#team focus