Question
If burndown charts are used to visualize progress, what does a trendline through a release burndown chart indicate?
Options
- AWhen all work will be completed so the Scrum Team can start work on a new Product Backlog.
- BWhen the project will be over if the Product Owner removes work that is equal in effort to any new
- CWhen the work remaining is projected to be completed if nothing changes on the Product Backlog
- DThe evolution of the return of investment on the project.