Steven is a Scrum Master asked to assist in creating five new Scrum Teams that will be working to build a highly anticipated product. He talks with them about the importance of being able to…

The correct answer is C. All Scrum Teams agree on a mutual understanding of `done' that defines all work necessary to. When a Product Backlog item or an Increment is described as "Done", everyone must understand what "Done" means. If there are multiple Scrum Teams working on the system or product release, the Development Teams on all the Scrum Teams must mutually define the definition of "Done"…

Scaling Scrum

Question

Steven is a Scrum Master asked to assist in creating five new Scrum Teams that will be working to build a highly anticipated product. He talks with them about the importance of being able to integrate their Increments by the end of their Sprints. This includes the first Sprints. The product is very important to both the end users and the organization. Of the choices raised by future team members, what would Steven encourage?

Options

  • AEach Scrum Team delivers Increments in its own code branch. After UAT is performed at the
  • BEach Scrum Team delivers functionality at the end of each Sprint. New Product Backlog items will
  • CAll Scrum Teams agree on a mutual understanding of `done' that defines all work necessary to
  • DWait until enough of the infrastructure and architecture is in place before starting the first Sprints.

How the community answered

(35 responses)
  • A
    17% (6)
  • B
    6% (2)
  • C
    71% (25)
  • D
    6% (2)

Explanation

When a Product Backlog item or an Increment is described as "Done", everyone must understand what "Done" means. If there are multiple Scrum Teams working on the system or product release, the Development Teams on all the Scrum Teams must mutually define the definition of "Done" to have a shared understanding of what it means for work to be complete, to ensure transparency. Each Increment is additive to all prior Increments and thoroughly tested, ensuring that all Increments work together.

Topics

#Definition of Done#integrated Increment#scaled teams#Sprint integration