Question

Steven is a Scrum Master asked to assist in creating five new Scrum Teams that will be working to build a highly anticipated product. He talks with them about the importance of being able to integrate their Increments by the end of their Sprints. This includes the first Sprints. The product is very important to both the end users and the organization. Of the choices raised by future team members, what would Steven encourage?

Options

  • AEach Scrum Team delivers Increments in its own code branch. After UAT is performed at the
  • BEach Scrum Team delivers functionality at the end of each Sprint. New Product Backlog items will
  • CAll Scrum Teams agree on a mutual understanding of `done' that defines all work necessary to
  • DWait until enough of the infrastructure and architecture is in place before starting the first Sprints.

Unlock PSM-II to see the answer