PSM-II · Question #114

What might be a valid reason for abnormally cancelling a Sprint?

The correct answer is D. When the Sprint Goal becomes obsolete. According to the Scrum Guide, only the Product Owner has the authority to cancel a Sprint, and the sole valid reason is that the Sprint Goal has become obsolete - meaning the goal no longer aligns with the company's direction, market conditions, or stakeholder needs, making…

Applying Scrum

Question

What might be a valid reason for abnormally cancelling a Sprint?

Options

  • AWhen the Development Team discovers it cannot meet their Sprint commitments.
  • BWhen the work becomes too difficult for the Development Team.
  • CWhen the sales department discovers features that add more value than the current work being
  • DWhen the Sprint Goal becomes obsolete.

How the community answered

(57 responses)
  • A
    2% (1)
  • B
    9% (5)
  • C
    4% (2)
  • D
    86% (49)

Explanation

According to the Scrum Guide, only the Product Owner has the authority to cancel a Sprint, and the sole valid reason is that the Sprint Goal has become obsolete - meaning the goal no longer aligns with the company's direction, market conditions, or stakeholder needs, making further work pointless.

Why the distractors are wrong:

  • A - Teams routinely adjust scope during a Sprint when they can't meet all commitments; that's normal, not a cancellation trigger.
  • B - Difficulty is never grounds for cancellation; the team works through challenges, possibly descoping lower-priority items.
  • C - Discovering higher-value features is handled through the Product Backlog, not by cancelling the Sprint; those items get prioritized for a future Sprint.

Memory tip: Think of Sprint cancellation as a "mission abort" - you only abort when the mission itself (the Sprint Goal) is no longer worth completing, not because of execution difficulties or new opportunities discovered along the way.

Topics

#Sprint cancellation#Sprint Goal obsolete#abnormal termination#Product Owner