PSM-II · Question #114
What might be a valid reason for abnormally cancelling a Sprint?
The correct answer is D. When the Sprint Goal becomes obsolete. According to the Scrum Guide, only the Product Owner has the authority to cancel a Sprint, and the sole valid reason is that the Sprint Goal has become obsolete - meaning the goal no longer aligns with the company's direction, market conditions, or stakeholder needs, making…
Question
What might be a valid reason for abnormally cancelling a Sprint?
Options
- AWhen the Development Team discovers it cannot meet their Sprint commitments.
- BWhen the work becomes too difficult for the Development Team.
- CWhen the sales department discovers features that add more value than the current work being
- DWhen the Sprint Goal becomes obsolete.
How the community answered
(57 responses)- A2% (1)
- B9% (5)
- C4% (2)
- D86% (49)
Explanation
According to the Scrum Guide, only the Product Owner has the authority to cancel a Sprint, and the sole valid reason is that the Sprint Goal has become obsolete - meaning the goal no longer aligns with the company's direction, market conditions, or stakeholder needs, making further work pointless.
Why the distractors are wrong:
- A - Teams routinely adjust scope during a Sprint when they can't meet all commitments; that's normal, not a cancellation trigger.
- B - Difficulty is never grounds for cancellation; the team works through challenges, possibly descoping lower-priority items.
- C - Discovering higher-value features is handled through the Product Backlog, not by cancelling the Sprint; those items get prioritized for a future Sprint.
Memory tip: Think of Sprint cancellation as a "mission abort" - you only abort when the mission itself (the Sprint Goal) is no longer worth completing, not because of execution difficulties or new opportunities discovered along the way.