PSM-II · Question #106
During the Sprint, the Development Team realizes they might not be able to finish all of the items in the Sprint Backlog. What should happen?
The correct answer is C. The Sprint length holds and the Development Team continuously learns what is actually possible. Option C is correct because in Scrum, the Sprint time-box is sacred and never extended. When the team realizes they've over-committed, the right response is to collaborate with the Product Owner to remove or reduce scope from the Sprint Backlog - not to extend the Sprint. This…
Question
During the Sprint, the Development Team realizes they might not be able to finish all of the items in the Sprint Backlog. What should happen?
Options
- AProduct Backlog items are either
done' ornot done.' This helps with transparency, reduces - BContinue Sprinting until the work is complete and redefine a new Sprint time-box based on the
- CThe Sprint length holds and the Development Team continuously learns what is actually possible
How the community answered
(29 responses)- A7% (2)
- B14% (4)
- C79% (23)
Explanation
Option C is correct because in Scrum, the Sprint time-box is sacred and never extended. When the team realizes they've over-committed, the right response is to collaborate with the Product Owner to remove or reduce scope from the Sprint Backlog - not to extend the Sprint. This constraint forces continuous learning: teams get better at forecasting over time precisely because the boundary is held firm.
Option A is partially true (transparency around "done/not done" is a Scrum value), but it describes an outcome or principle, not an action the team should take in the moment - and the answer appears incomplete.
Option B is wrong because extending the Sprint to finish all work destroys the core purpose of time-boxing. Redefining the Sprint length based on how long work actually takes turns Scrum into an open-ended project with no feedback cadence.
Memory tip: Think of a Sprint like a TV episode slot - the show airs at the scheduled time no matter what. If the script is too long, you cut scenes (scope), you don't push the broadcast date. Fixed time, variable scope.
Topics
Community Discussion
No community discussion yet for this question.