PSM-II · Question #103

What are typical Product Owner activities during Sprint 0?

The correct answer is E. There is no such thing as Sprint. There are no special Sprints. All Sprints are structured to produce potentially shippable product

Applying Scrum

Question

What are typical Product Owner activities during Sprint 0?

Options

  • ACreating a project plan based on the defined timeline.
  • BEnsuring there is enough work to do for at least three Sprints.
  • CCreating User Stories based on the requirements document.
  • DAllocating enough resources before starting Sprint 1.
  • EThere is no such thing as Sprint.

How the community answered

(52 responses)
  • A
    6% (3)
  • B
    2% (1)
  • D
    2% (1)
  • E
    90% (47)

Explanation

There are no special Sprints. All Sprints are structured to produce potentially shippable product

Topics

#Sprint 0#Scrum myths#empiricism#Product Owner role