nerdexam
Scrum

PSM-I · Question #92

Scrum has a role called "Project Manager".

The correct answer is B. False. The correct answer is B, because there is no role called "Project Manager" in Scrum. The Scrum Guide states that "Scrum recognizes no titles for Development Team members other than Developer, regardless of the work being performed by the person; there are no exceptions to this…

Submitted by fernanda_arg· Apr 18, 2026Scrum Framework

Question

Scrum has a role called "Project Manager".

Options

  • ATrue
  • BFalse

How the community answered

(35 responses)
  • A
    14% (5)
  • B
    86% (30)

Explanation

The correct answer is B, because there is no role called "Project Manager" in Scrum. The Scrum Guide states that "Scrum recognizes no titles for Development Team members other than Developer, regardless of the work being performed by the person; there are no exceptions to this rule." Therefore, Scrum has only three roles: Product Owner, Scrum Master, and Developer.

Topics

#Scrum Roles#Scrum Team#Scrum Framework Basics

Community Discussion

No community discussion yet for this question.

Full PSM-I Practice