PSM-I · Question #73
What activities would a Product Owner typically undertake in the phase between the end of the current Sprint and the start of the next Sprint?
The correct answer is A. There are no such activities. The next Sprint starts immediately after the current Sprint. There are no activities that a Product Owner would typically undertake in the phase between the end of the current Sprint and the start of the next Sprint, because there is no such phase. The next Sprint starts immediately after the current Sprint, without any gaps or breaks…
Question
What activities would a Product Owner typically undertake in the phase between the end of the current Sprint and the start of the next Sprint?
Options
- AThere are no such activities. The next Sprint starts immediately after the current Sprint.
- BRefine the Product Backlog.
- CWork with the Quality Assurance departments on the Increment of the current Sprint.
- DUpdate the project plan with stakeholders.
How the community answered
(36 responses)- A89% (32)
- B6% (2)
- C3% (1)
- D3% (1)
Explanation
There are no activities that a Product Owner would typically undertake in the phase between the end of the current Sprint and the start of the next Sprint, because there is no such phase. The next Sprint starts immediately after the current Sprint, without any gaps or breaks. The other options are either activities that occur during a Sprint (such as refining the Product Backlog) or activities that are not consistent with Scrum (such as working with Quality Assurance departments or updating project plans).
Topics
Community Discussion
No community discussion yet for this question.