PSM-I · Question #51

What two techniques could the Scrum Master use when the Scrum Team gets caught in an internal disagreement about which development techniques to apply? (Choose two.)

The correct answer is A. Involve the complete Development Team. B. Use coaching techniques; such as open questions and active listening. A (Involve the complete Development Team) is correct because Scrum values collective ownership and self-organization - the whole team deciding together produces buy-in and leverages diverse perspectives. B (Use coaching techniques like open questions and active listening) is…

Submitted by ahmad_uae· Apr 18, 2026Developing People and Teams

Question

What two techniques could the Scrum Master use when the Scrum Team gets caught in an internal disagreement about which development techniques to apply? (Choose two.)

Options

  • AInvolve the complete Development Team.
  • BUse coaching techniques; such as open questions and active listening.
  • CAsk an external technical specialist to make the decision.
  • DSend every team member to the company's HR department to express their concerns.

How the community answered

(27 responses)
  • A
    70% (19)
  • C
    7% (2)
  • D
    22% (6)

Explanation

A (Involve the complete Development Team) is correct because Scrum values collective ownership and self-organization - the whole team deciding together produces buy-in and leverages diverse perspectives. B (Use coaching techniques like open questions and active listening) is correct because the Scrum Master's role is a servant-leader and coach, not a decision-maker; these techniques surface the team's own wisdom without imposing a solution.

C is wrong because bringing in an external specialist to make the decision bypasses the team's self-organizing principle - external input for information is fine, but decision authority belongs to the team. D is wrong because HR involvement is entirely outside the Scrum framework and would escalate a technical disagreement into a personnel matter, which is counterproductive and inappropriate.

Memory tip: Think "inside-out" - the Scrum Master always works within the team first (involve the team = A) and uses facilitative skills rather than directive ones (coaching = B). Any answer that hands power to someone outside the team (external specialist, HR) contradicts Scrum's self-organization principle.

Topics

#Scrum Master Role#Team Self-organization#Conflict Resolution#Coaching

Community Discussion

No community discussion yet for this question.