PSM-I · Question #5

Which three of the following are feedback loops in Scrum? (Choose three.)

The correct answer is A. Sprint Review. C. Sprint Retrospective. E. Daily Scrum. The correct answers are A, C, and E, because these are feedback loops in Scrum. The Sprint Review is a feedback loop that allows the Scrum Team and the stakeholders to inspect the Increment and adapt the Product Backlog. The Sprint Retrospective is a feedback loop that allows…

Submitted by viktor_hu· Apr 18, 2026Scrum Framework

Question

Which three of the following are feedback loops in Scrum? (Choose three.)

Options

  • ASprint Review.
  • BRelease Planning.
  • CSprint Retrospective.
  • DRefinement Meeting.
  • EDaily Scrum.

How the community answered

(35 responses)
  • A
    94% (33)
  • B
    3% (1)
  • D
    3% (1)

Explanation

The correct answers are A, C, and E, because these are feedback loops in Scrum. The Sprint Review is a feedback loop that allows the Scrum Team and the stakeholders to inspect the Increment and adapt the Product Backlog. The Sprint Retrospective is a feedback loop that allows the Scrum Team to inspect itself and create a plan for improvements. The Daily Scrum is a feedback loop that allows the Development Team to inspect its progress and plan its work for the

Topics

#Scrum Events#Feedback Loops#Daily Scrum#Sprint Review