The correct answer is A: Sprint Review.. The correct answers are A, C, and E, because these are feedback loops in Scrum. The Sprint Review is a feedback loop that allows the Scrum Team and the stakeholders to inspect the Increment and adapt the Product Backlog. The Sprint Retrospective is a feedback loop that allows the
Question
Which three of the following are feedback loops in Scrum? (Choose three.)
Options
- ASprint Review.
- BRelease Planning.
- CSprint Retrospective.
- DRefinement Meeting.
- EDaily Scrum.
Explanation
The correct answers are A, C, and E, because these are feedback loops in Scrum. The Sprint Review is a feedback loop that allows the Scrum Team and the stakeholders to inspect the Increment and adapt the Product Backlog. The Sprint Retrospective is a feedback loop that allows the Scrum Team to inspect itself and create a plan for improvements. The Daily Scrum is a feedback loop that allows the Development Team to inspect its progress and plan its work for the
Topics
Community Discussion
No community discussion yet for this question.