PSM-I · Question #5

PSM-I Question #5: Real Exam Question with Answer & Explanation

The correct answer is A: Sprint Review.. The correct answers are A, C, and E, because these are feedback loops in Scrum. The Sprint Review is a feedback loop that allows the Scrum Team and the stakeholders to inspect the Increment and adapt the Product Backlog. The Sprint Retrospective is a feedback loop that allows the

Submitted by viktor_hu· Apr 18, 2026Scrum Framework

Question

Which three of the following are feedback loops in Scrum? (Choose three.)

Options

  • ASprint Review.
  • BRelease Planning.
  • CSprint Retrospective.
  • DRefinement Meeting.
  • EDaily Scrum.

Explanation

The correct answers are A, C, and E, because these are feedback loops in Scrum. The Sprint Review is a feedback loop that allows the Scrum Team and the stakeholders to inspect the Increment and adapt the Product Backlog. The Sprint Retrospective is a feedback loop that allows the Scrum Team to inspect itself and create a plan for improvements. The Daily Scrum is a feedback loop that allows the Development Team to inspect its progress and plan its work for the

Topics

#Scrum Events#Feedback Loops#Daily Scrum#Sprint Review