The correct answer is D: The Scrum Team is responsible. In Scrum, the Scrum Team is self-organizing, which includes responsibility for its own composition and internal conflicts. If a Developer's ongoing conflicts impact delivery, the Scrum Team as a whole is responsible for resolving this - including removing a member if necessary. O
Question
A new Developer is having continuing conflicts with existing members or the scrum Team, which is impacting the delivery of the Increment It necessary, who is responsible for removing the Developer from the Scrum Team? (Choose the best answer)
Options
- AThe Scrum Master is responsible, they remove impediments
- BThe Product Owner is responsible, they control the return on investment (ROI)
- CThe hiring manager is responsible, they hired the Developer
- DThe Scrum Team is responsible
Explanation
In Scrum, the Scrum Team is self-organizing, which includes responsibility for its own composition and internal conflicts. If a Developer's ongoing conflicts impact delivery, the Scrum Team as a whole is responsible for resolving this - including removing a member if necessary. Option A is incorrect because the Scrum Master's impediment-removal role is about process and organizational blockers, not personnel decisions. Option B is wrong because the Product Owner manages the product backlog and ROI, not team membership. Option C is wrong because Scrum does not assign team management authority to a hiring manager - once someone joins a Scrum Team, the team governs itself.