The correct answer is A: what have we learned since yesterday, and now should we modify our plan to increase our ability. Three topics for the Developers to discuss at the Daily Scrum as they inspect their progress toward the Sprint Goal are: What have we learned since yesterday, and how should we modify our plan to increase our ability to meet the Sprint Goal? Are there any impediments blocking pro
Question
Which of the following are topics for the Developers to discuss at the Daily scrum as they inspect their progress toward the Sprint Goal? (Choose the best three answers)
Options
- Awhat have we learned since yesterday, and now should we modify our plan to increase our ability
- BAre mere any impediments Clocking progress toward the sprint Goal?
- CWhat will I be working on tomorrow?
- DAre mere any decisions that need to be made to maintain progress toward the sprint Goal?
- EWhy were you late?
- FHow many hours Old I spend on the project yesterday
- Gwin todays work negatively impact our ability to meet the sprint Goal for the Split following this
Explanation
Three topics for the Developers to discuss at the Daily Scrum as they inspect their progress toward the Sprint Goal are: What have we learned since yesterday, and how should we modify our plan to increase our ability to meet the Sprint Goal? Are there any impediments blocking progress toward the Sprint Goal? Are there any decisions that need to be made to maintain progress toward the Sprint Goal? These topics are suggested by: "The structure of the meeting is set by the Developers and can be conducted in different ways if it focuses on progress toward the Sprint Goal. Some Development Teams will use questions, some will be more discussion based."