PSM-I · Question #249

PSM-I Question #249: Real Exam Question with Answer & Explanation

The correct answer is D: When the item meets the Definition of Done. A Product Backlog item is considered complete when it meets the Definition of Done, as stated in: "When a Product Backlog item or an Increment is described as "Done", everyone must understand what "Done" means. Although this varies significantly per Scrum Team, members must have

Submitted by krish.m· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

When is a Product Backlog item considered complete? (Choose the best answer)

Options

  • AWhen the item passes ail acceptance criteria
  • BWhen the item has gamed product sponsor approval
  • CAt the end of the Sprint
  • DWhen the item meets the Definition of Done

Explanation

A Product Backlog item is considered complete when it meets the Definition of Done, as stated in: "When a Product Backlog item or an Increment is described as "Done", everyone must understand what "Done" means. Although this varies significantly per Scrum Team, members must have a shared understanding of what it means for work to be complete, to ensure transparency. This is the definition of "Done" for the Scrum Team and is used to assess when work is complete on the product Increment."

Topics

#Definition of Done#Product Backlog Item#Increment#Scrum Artifacts

Community Discussion

No community discussion yet for this question.