PSM-I · Question #251
PSM-I Question #251: Real Exam Question with Answer & Explanation
The correct answer is B: False. According to the Scrum Guide, a high-performance Scrum Team does not run a Release Sprint, as this is not a Scrum event. A Release Sprint is a term used to describe a Sprint that is dedicated to finalizing the product for release, such as fixing bugs, polishing features, or integ
Question
True or False A high-performance scrum Team ensures that each increment is complete by running a Release Sprint.
Options
- ATrue
- BFalse
Explanation
According to the Scrum Guide, a high-performance Scrum Team does not run a Release Sprint, as this is not a Scrum event. A Release Sprint is a term used to describe a Sprint that is dedicated to finalizing the product for release, such as fixing bugs, polishing features, or integrating components. This is contrary to the Scrum principle of delivering a potentially releasable Increment at the end of each Sprint, regardless of whether it is actually released or not. Therefore, the answer is false.
Topics
Community Discussion
No community discussion yet for this question.