PSM-I · Question #245

PSM-I Question #245: Real Exam Question with Answer & Explanation

The correct answer is B: Never am Developers on the Scrum Team share accountability tor items in the. In Scrum, no individual Developer is assigned ownership of a specific Sprint Backlog item. The entire Development Team holds collective accountability for all Sprint Backlog items and achieving the Sprint Goal together. Option A (Daily Scrum) is wrong because the Daily Scrum is a

Submitted by rania.sa· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

When does a Developer become accountable for an item in the sprint Backlog? (Choose the best answer)

Options

  • ADuring the Daily Scrum
  • BNever am Developers on the Scrum Team share accountability tor items in the
  • CAs soon as a Developer on the Scrum Team can accommodate more work
  • DAt Sprint Planning when all of the Sprint Backlog items are split evenly across the Developers

Explanation

In Scrum, no individual Developer is assigned ownership of a specific Sprint Backlog item. The entire Development Team holds collective accountability for all Sprint Backlog items and achieving the Sprint Goal together. Option A (Daily Scrum) is wrong because the Daily Scrum is an inspection and adaptation event, not an assignment ceremony. Option C implies individual capacity triggers ownership, which is inconsistent with team-level accountability. Option D (items split evenly at Sprint Planning) violates Scrum principles - Sprint Backlog items are not divided among individuals. The Developers self-organize to determine who works on what, but accountability remains shared.

Topics

#Scrum Team#Developers#Accountability#Sprint Backlog