True or False: A scrum Master Fulfills me same role as a traditional project Manager.

The correct answer is B. False. A Scrum Master fulfills a different role than a traditional project manager, as stated in: "A project manager helps manage the project timeline, resources, and scope in order to meet business requirements. A Scrum Master, however, helps ensure the Scrum Team follows Scrum…

Submitted by tunde_lagos· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

True or False: A scrum Master Fulfills me same role as a traditional project Manager.

Options

  • ATrue
  • BFalse

How the community answered

(47 responses)
  • A
    15% (7)
  • B
    85% (40)

Explanation

A Scrum Master fulfills a different role than a traditional project manager, as stated in: "A project manager helps manage the project timeline, resources, and scope in order to meet business requirements. A Scrum Master, however, helps ensure the Scrum Team follows Scrum theory, practices, and rules. The Scrum Master is a servant-leader who helps optimize the value created by the Scrum Team."

Topics

#Scrum Master Role#Project Manager Role#Role Differences#Scrum Framework