PSM-I · Question #244
Who determines how many Product Backlog items the Developers select tor a sprint? (Choose the best answer)
The correct answer is C. The Developers. The Developers determine how many Product Backlog items they select for a Sprint, as stated in the Scrum Guide: "The Developers select items from the Product Backlog to include in the current Sprint. The Scrum Team may refine these items during this process, which increases…
Question
Who determines how many Product Backlog items the Developers select tor a sprint? (Choose the best answer)
Options
- AThe Scrum Master
- BThe Scrum Team
- CThe Developers
- DThe stakeholders attending Sprint Planning
- EThe Product Owner
How the community answered
(30 responses)- A3% (1)
- C87% (26)
- D3% (1)
- E7% (2)
Explanation
The Developers determine how many Product Backlog items they select for a Sprint, as stated in the Scrum Guide: "The Developers select items from the Product Backlog to include in the current Sprint. The Scrum Team may refine these items during this process, which increases understanding and confidence."