What is the time-box for the Sprint Planning meeting?
The correct answer is B. 8 Hours for a monthly Sprint. The correct answer is B, because the time-box for the Sprint Planning meeting is 8 hours for a monthly Sprint. The Scrum Guide states that "Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the event is usually shorter."
Submitted by neha2k· Apr 18, 2026Scrum Framework
Question
What is the time-box for the Sprint Planning meeting?
Options
- A4 Hours for a monthly Sprint.
- B8 Hours for a monthly Sprint.
- CMonthly.
- DWhenever it is done.
How the community answered
(34 responses)- B91% (31)
- C3% (1)
- D6% (2)
Explanation
The correct answer is B, because the time-box for the Sprint Planning meeting is 8 hours for a monthly Sprint. The Scrum Guide states that "Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the event is usually shorter."