The correct answer is A. Sprint Backlog B. Increment E. Product Backlog. The Scrum Guide defines exactly three Scrum Artifacts: the Product Backlog (E), the Sprint Backlog (A), and the Increment (B). The Sprint Goal (C) is the objective of the Sprint and serves as a commitment for the Sprint Backlog, but it is not itself an artifact. A list of…
Question
What are the Scrum Artifacts? Select all applicable items.
Options
- ASprint Backlog
- BIncrement
- CThe Sprint Goal
- DThe list of removed impediments
- EProduct Backlog
How the community answered
(54 responses)- A91% (49)
- C4% (2)
- D6% (3)
Explanation
The Scrum Guide defines exactly three Scrum Artifacts: the Product Backlog (E), the Sprint Backlog (A), and the Increment (B). The Sprint Goal (C) is the objective of the Sprint and serves as a commitment for the Sprint Backlog, but it is not itself an artifact. A list of removed impediments (D) has no formal standing in Scrum at all - it is neither an artifact nor a required output of any Scrum event.
Topics
Community Discussion
No community discussion yet for this question.