What are the questions the Sprint Planning answers? Select two.
The correct answer is D. How will the work needed to deliver the Increment be achieved? E. What can be delivered in the Increment resulting from the upcoming Sprint? According to the Scrum Guide, Sprint Planning addresses two core questions: (E) 'What can be delivered in the Increment resulting from the upcoming Sprint?' - the team and Product Owner collaborate to select Product Backlog items that can be completed, defining the Sprint Goal…
Question
What are the questions the Sprint Planning answers? Select two.
Options
- AWhat is the size of the Technical Debt and how it could be removed?
- BWhat new technologies could be used to speed up the Development Team velocity?
- CWho will be responsible for each item in the Sprint Backlog?
- DHow will the work needed to deliver the Increment be achieved?
- EWhat can be delivered in the Increment resulting from the upcoming Sprint?
How the community answered
(52 responses)- A2% (1)
- B6% (3)
- C2% (1)
- D90% (47)
Explanation
According to the Scrum Guide, Sprint Planning addresses two core questions: (E) 'What can be delivered in the Increment resulting from the upcoming Sprint?' - the team and Product Owner collaborate to select Product Backlog items that can be completed, defining the Sprint Goal; (D) 'How will the work needed to deliver the Increment be achieved?' - the Development Team plans the technical approach, decomposing selected items into tasks. Options A and B are not Sprint Planning questions - technical debt and new technologies may be discussed but are not the defined purpose. Option C (assigning responsibility per item) contradicts self-organization; the team collectively owns the Sprint Backlog.