The correct answer is D: How will the work needed to deliver the Increment be achieved?. According to the Scrum Guide, Sprint Planning addresses two core questions: (E) 'What can be delivered in the Increment resulting from the upcoming Sprint?' — the team and Product Owner collaborate to select Product Backlog items that can be completed, defining the Sprint Goal;

Submitted by certguy· Apr 18, 2026Scrum Framework

Question

What are the questions the Sprint Planning answers? Select two.

Options

  • AWhat is the size of the Technical Debt and how it could be removed?
  • BWhat new technologies could be used to speed up the Development Team velocity?
  • CWho will be responsible for each item in the Sprint Backlog?
  • DHow will the work needed to deliver the Increment be achieved?
  • EWhat can be delivered in the Increment resulting from the upcoming Sprint?

Explanation

According to the Scrum Guide, Sprint Planning addresses two core questions: (E) 'What can be delivered in the Increment resulting from the upcoming Sprint?' — the team and Product Owner collaborate to select Product Backlog items that can be completed, defining the Sprint Goal; (D) 'How will the work needed to deliver the Increment be achieved?' — the Development Team plans the technical approach, decomposing selected items into tasks. Options A and B are not Sprint Planning questions — technical debt and new technologies may be discussed but are not the defined purpose. Option C (assigning responsibility per item) contradicts self-organization; the team collectively owns the Sprint Backlog.