PSM-I · Question #160

Who participates in the Sprint Review? Select all applicable variants.

The correct answer is A. The Development Team B. The Scrum Master D. The Key Stakeholders E. The Product Owner. The Sprint Review is an inspect-and-adapt event for the Increment. The required and typical participants are: the Development Team (A), who demonstrates the work; the Scrum Master (B), who facilitates; Key Stakeholders (D), who provide feedback; and the Product Owner (E), who…

Submitted by andreas_gr· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

Who participates in the Sprint Review? Select all applicable variants.

Options

  • AThe Development Team
  • BThe Scrum Master
  • CThe Organization CEO
  • DThe Key Stakeholders
  • EThe Product Owner

How the community answered

(40 responses)
  • A
    88% (35)
  • C
    13% (5)

Explanation

The Sprint Review is an inspect-and-adapt event for the Increment. The required and typical participants are: the Development Team (A), who demonstrates the work; the Scrum Master (B), who facilitates; Key Stakeholders (D), who provide feedback; and the Product Owner (E), who leads the discussion and updates the backlog. The Organization CEO (C) is not excluded by rule, but is not a standard or required participant - 'Key Stakeholders' already covers relevant business representatives. The CEO as a generic role is not listed among those Scrum identifies for this event.

Topics

#Sprint Review#Scrum Events#Scrum Roles#Stakeholders