The correct answer is A: The Development Team. The Sprint Review is an inspect-and-adapt event for the Increment. The required and typical participants are: the Development Team (A), who demonstrates the work; the Scrum Master (B), who facilitates; Key Stakeholders (D), who provide feedback; and the Product Owner (E), who lea

Submitted by andreas_gr· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

Who participates in the Sprint Review? Select all applicable variants.

Options

  • AThe Development Team
  • BThe Scrum Master
  • CThe Organization CEO
  • DThe Key Stakeholders
  • EThe Product Owner

Explanation

The Sprint Review is an inspect-and-adapt event for the Increment. The required and typical participants are: the Development Team (A), who demonstrates the work; the Scrum Master (B), who facilitates; Key Stakeholders (D), who provide feedback; and the Product Owner (E), who leads the discussion and updates the backlog. The Organization CEO (C) is not excluded by rule, but is not a standard or required participant — 'Key Stakeholders' already covers relevant business representatives. The CEO as a generic role is not listed among those Scrum identifies for this event.

Topics

#Sprint Review#Scrum Events#Scrum Roles#Stakeholders