The correct answer is A: Any completed and "Done" Product Backlog items are reviewed. When a Sprint is cancelled, three things happen: (A) completed and 'Done' Product Backlog items are reviewed to determine if they can be accepted; (B) all incomplete Product Backlog Items are re-estimated and returned to the Product Backlog; and (C) if part of the work is potenti
Question
What happens when a Sprint is cancelled? Select three.
Options
- AAny completed and "Done" Product Backlog items are reviewed
- BAll incomplete Product Backlog Items are re-estimated and put back on the Product Backlog
- CIf part of the work is potentially releasable, the Product Owner typically accepts it
- DSeveral top Product Backlog Items are taken into the Sprint Backlog to replace the obsolete items
- EAt the Sprint Retrospective the Scrum Master determines who from the Development Team is
Explanation
When a Sprint is cancelled, three things happen: (A) completed and 'Done' Product Backlog items are reviewed to determine if they can be accepted; (B) all incomplete Product Backlog Items are re-estimated and returned to the Product Backlog; and (C) if part of the work is potentially releasable, the Product Owner typically accepts it. Option D is incorrect — no new Sprint Backlog items are pulled during cancellation. Option E is incorrect — the Scrum Master does not determine personnel changes; Sprint Retrospectives assess process, not staffing decisions.