PSM-I · Question #159
Who is allowed to participate in the Daily Scrum?
The correct answer is C. The Development Team. The Daily Scrum is an event owned by and intended for the Development Team (C). They use it to inspect progress toward the Sprint Goal and adapt their plan for the next 24 hours. The Scrum Master (A) may attend to ensure the event occurs and stays within the 15-minute timebox…
Question
Who is allowed to participate in the Daily Scrum?
Options
- AThe Scrum Master
- BThe Key Stakeholders
- CThe Development Team
- DThe Product Owner
How the community answered
(55 responses)- A5% (3)
- B2% (1)
- C91% (50)
- D2% (1)
Explanation
The Daily Scrum is an event owned by and intended for the Development Team (C). They use it to inspect progress toward the Sprint Goal and adapt their plan for the next 24 hours. The Scrum Master (A) may attend to ensure the event occurs and stays within the 15-minute timebox, but does not run it. The Product Owner (D) and Key Stakeholders (B) are not required participants. If others attend, they observe but do not participate in the discussion - the Development Team conducts the meeting.
Topics