The correct answer is B: The Product Owner. Only the Product Owner has the authority to cancel a Sprint, although they may do so under influence from stakeholders, the Development Team, or the Scrum Master. A Sprint may be cancelled if the Sprint Goal becomes obsolete — for example, due to a change in business direction

Submitted by eva_at· Apr 18, 2026Scrum Framework

Question

Who has the authority to cancel the Sprint?

Options

  • AThe Development Team
  • BThe Product Owner
  • CThe Product Owner and the Scrum Master
  • DThe Scrum Master
  • EThe Key Stakeholders

Explanation

Only the Product Owner has the authority to cancel a Sprint, although they may do so under influence from stakeholders, the Development Team, or the Scrum Master. A Sprint may be cancelled if the Sprint Goal becomes obsolete — for example, due to a change in business direction or market conditions. Sprint cancellations are rare and generally disruptive. The Scrum Master, Development Team, and stakeholders do not have cancellation authority — this power rests solely with the Product Owner as the person accountable for the product's value.