The correct answer is B: The Product Owner. Only the Product Owner has the authority to cancel a Sprint, although they may do so under influence from stakeholders, the Development Team, or the Scrum Master. A Sprint may be cancelled if the Sprint Goal becomes obsolete — for example, due to a change in business direction
Question
Who has the authority to cancel the Sprint?
Options
- AThe Development Team
- BThe Product Owner
- CThe Product Owner and the Scrum Master
- DThe Scrum Master
- EThe Key Stakeholders
Explanation
Only the Product Owner has the authority to cancel a Sprint, although they may do so under influence from stakeholders, the Development Team, or the Scrum Master. A Sprint may be cancelled if the Sprint Goal becomes obsolete — for example, due to a change in business direction or market conditions. Sprint cancellations are rare and generally disruptive. The Scrum Master, Development Team, and stakeholders do not have cancellation authority — this power rests solely with the Product Owner as the person accountable for the product's value.
Topics
Community Discussion
No community discussion yet for this question.