nerdexam
Scrum

PSM-I · Question #128

How long should the Sprint Planning be?

The correct answer is D. Not more than 8 hours. Sprint Planning is time-boxed to a maximum of 8 hours for a one-month Sprint. For shorter Sprints, the event is usually proportionally shorter - for example, a two-week Sprint would typically have a 4-hour Sprint Planning. Option A describes Product Backlog refinement capacity…

Submitted by andres_qro· Apr 18, 2026Scrum Framework

Question

How long should the Sprint Planning be?

Options

  • ANot more than 10% of the capacity of the Development Team
  • BUntil all the Items in the Sprint Backlog are decomposed to units of one day or less
  • CNot more than 4 hours
  • DNot more than 8 hours

How the community answered

(22 responses)
  • B
    5% (1)
  • C
    5% (1)
  • D
    91% (20)

Explanation

Sprint Planning is time-boxed to a maximum of 8 hours for a one-month Sprint. For shorter Sprints, the event is usually proportionally shorter - for example, a two-week Sprint would typically have a 4-hour Sprint Planning. Option A describes Product Backlog refinement capacity, not Sprint Planning. Option B refers to a practice that may occur during planning but is not the time-box definition. Option C (4 hours) would apply to shorter Sprints but is not the defined maximum.

Topics

#Sprint Planning#Scrum Events#Time-boxing

Community Discussion

No community discussion yet for this question.

Full PSM-I Practice