PSM-I · Question #128
How long should the Sprint Planning be?
The correct answer is D. Not more than 8 hours. Sprint Planning is time-boxed to a maximum of 8 hours for a one-month Sprint. For shorter Sprints, the event is usually proportionally shorter - for example, a two-week Sprint would typically have a 4-hour Sprint Planning. Option A describes Product Backlog refinement capacity…
Question
How long should the Sprint Planning be?
Options
- ANot more than 10% of the capacity of the Development Team
- BUntil all the Items in the Sprint Backlog are decomposed to units of one day or less
- CNot more than 4 hours
- DNot more than 8 hours
How the community answered
(22 responses)- B5% (1)
- C5% (1)
- D91% (20)
Explanation
Sprint Planning is time-boxed to a maximum of 8 hours for a one-month Sprint. For shorter Sprints, the event is usually proportionally shorter - for example, a two-week Sprint would typically have a 4-hour Sprint Planning. Option A describes Product Backlog refinement capacity, not Sprint Planning. Option B refers to a practice that may occur during planning but is not the time-box definition. Option C (4 hours) would apply to shorter Sprints but is not the defined maximum.
Topics
Community Discussion
No community discussion yet for this question.