PSM-I · Question #1

PSM-I Question #1: Real Exam Question with Answer & Explanation

The correct answer is C: The Scrum Team and stakeholders.. According to the Scrum Guide, the Sprint Review is an informal meeting at the end of the Sprint, where the Scrum Team and stakeholders collaborate about what was done in the Sprint. Based on that and any changes to the Product Backlog during the Sprint, attendees collaborate on w

Submitted by devops_kid· Apr 18, 2026Scrum Framework

Question

The Sprint Review is mainly an inspect and adapt opportunity for which group?

Options

  • AThe Development Team and stakeholders.
  • BThe Product Owner and Development Team.
  • CThe Scrum Team and stakeholders.
  • DThe Product Owner and management.
  • EThe Development Team and management.
  • FThe Product Owner and stakeholders.

Explanation

According to the Scrum Guide, the Sprint Review is an informal meeting at the end of the Sprint, where the Scrum Team and stakeholders collaborate about what was done in the Sprint. Based on that and any changes to the Product Backlog during the Sprint, attendees collaborate on what to do next. The Product Owner explains what Product Backlog items have been "Done" and what has not been "Done"; the Development Team discusses what went well during the Sprint, what problems it ran into, and how those problems were solved; and the Development Team demonstrates the work that it has "Done" and answers questions about the Increment. The entire group collaborates on what to do next, so that the Sprint Review provides valuable input to subsequent Sprint Planning. The Sprint Review is mainly an inspect and adapt opportunity for the Scrum Team and stakeholders.

Topics

#Sprint Review#Scrum Team#Stakeholders#Inspect and Adapt