PRINCE2-PRACTITIONER Exam Questions
315 real PRINCE2-PRACTITIONER exam questions with expert-verified answers and explanations. Page 7 of 7.
- Question #377Organization Theme
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
corporate governanceproject mandateexecutive authorityproject board - Question #378Risk Theme
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
risk actioneerisk responsecost-benefit of responseteam plan - Question #379Change Theme
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
configuration managementconfiguration item recordswork package completionproject manager notification - Question #380Tailoring PRINCE2 with Agile
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
agile tailoringsprint acceptanceproduct handoveruser acceptance - Question #381Quality Theme
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
project assurancequality management approachexecutive responsibilityquality theme - Question #382Managing a Stage Boundary Process
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
exception plantolerancesproject board escalationmanaging stage boundary - Question #383Change Theme
Project Scenario Health and Safety Training Project: ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses...
change budgetproject controlschange controltolerance setting - Question #394PRINCE2 Principles
has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to prov...
continued business justificationmanage by exceptionPRINCE2 principlescontrolling a stage - Question #396PRINCE2 Principles
The project is in stage 3. The BuildyBrick construction teams are unsure about using the required environmentally friendly concrete technique. As the team has not used the techniqu...
learn from experiencelessons learnedPRINCE2 principlesfield visit - Question #397PRINCE2 Principles
The project is nearing the end of stage 2. The Sustainability Manager records a lesson learned in the daily log that could be used on other projects in the portfolio. Is this an ap...
learn from experiencedaily loglessons learnedportfolio sharing - Question #399Organization Practice
The project executive delegates assurance of sustainability targets to the Sustainability Manager from the portfolio office. Is this an appropriate application of the organization...
organization practiceassurance delegationproject executiveaccountability - Question #400Quality Practice
A quality specification states: "The shopping centre will provide leisure and restroom space of a minimum of 2000." Is this an appropriate application of the quality practice, and...
quality practicequality specificationquality criteriaproduct description - Question #401Issues Practice
A concern about possible subsidence damage has been recorded as an issue. Is this an appropriate application of the issues practice, and why?
issues practiceissue managementrisk assessmentchange control - Question #402
A team manager forecasts a work package will exceed time tolerance and raises an issue. Is this appropriate application of the progress practice, and why?
- Question #403Directing a Project Process
The project board authorizes the project after reviewing the PID and business case. Is this appropriate application of Directing a Project?
directing a projectPID authorizationstage planproject board