PRINCE2-PRACTITIONER · Question #403

The project board authorizes the project after reviewing the PID and business case. Is this appropriate application of Directing a Project?

The correct answer is C. No, because the stage plan must also be approved. Explanation/Reference: PRINCE2 requires the project board to approve both the PID and the next stage plan before authorizing work. Without an approved stage plan, work cannot begin.

Directing a Project Process

Question

The project board authorizes the project after reviewing the PID and business case. Is this appropriate application of Directing a Project?

Options

  • AYes, PID authorization allows next stage work
  • BYes, notification replaces approval
  • CNo, because the stage plan must also be approved
  • DNo, because the council must approve

How the community answered

(45 responses)
  • A
    2% (1)
  • B
    4% (2)
  • C
    80% (36)
  • D
    13% (6)

Explanation

Explanation/Reference: PRINCE2 requires the project board to approve both the PID and the next stage plan before authorizing work. Without an approved stage plan, work cannot begin.

Topics

#directing a project#PID authorization#stage plan#project board