PRINCE2
PRINCE2-PRACTITIONER · Question #403
The project board authorizes the project after reviewing the PID and business case. Is this appropriate application of Directing a Project?
The correct answer is C. No, because the stage plan must also be approved. Explanation/Reference: PRINCE2 requires the project board to approve both the PID and the next stage plan before authorizing work. Without an approved stage plan, work cannot begin.
Directing a Project Process
Question
The project board authorizes the project after reviewing the PID and business case. Is this appropriate application of Directing a Project?
Options
- AYes, PID authorization allows next stage work
- BYes, notification replaces approval
- CNo, because the stage plan must also be approved
- DNo, because the council must approve
How the community answered
(45 responses)- A2% (1)
- B4% (2)
- C80% (36)
- D13% (6)
Explanation
Explanation/Reference: PRINCE2 requires the project board to approve both the PID and the next stage plan before authorizing work. Without an approved stage plan, work cannot begin.
Topics
#directing a project#PID authorization#stage plan#project board
Community Discussion
No community discussion yet for this question.