PRINCE2-PRACTITIONER · Question #402

A team manager forecasts a work package will exceed time tolerance and raises an issue. Is this appropriate application of the progress practice, and why?

See the full explanation below for the reasoning.

Question

A team manager forecasts a work package will exceed time tolerance and raises an issue. Is this appropriate application of the progress practice, and why?

Options

  • AYes, because forecast exceptions must be escalated
  • BYes, because planning should improve
  • CNo, because an exception report is required immediately
  • DNo, because escalation should wait