PRINCE2-PRACTITIONER · Question #399
PRINCE2-PRACTITIONER Question #399: Real Exam Question with Answer & Explanation
The correct answer is B. Yes, because assurance may be delegated to someone with expertise. Explanation/Reference: PRINCE2 clearly states that project assurance is the responsibility of the project board, but it may be delegated to individuals with appropriate skills and independence. The executive remains accountable but does not need to perform assurance activities pe
Question
Options
- AYes, to support manage by exception
- BYes, because assurance may be delegated to someone with expertise
- CNo, because the executive must do assurance personally
- DNo, because accountability cannot be delegated
Explanation
Explanation/Reference: PRINCE2 clearly states that project assurance is the responsibility of the project board, but it may be delegated to individuals with appropriate skills and independence. The executive remains accountable but does not need to perform assurance activities personally. The Sustainability Manager has relevant expertise and independence, making them a suitable delegate. Option B correctly reflects PRINCE2 organizational guidance. Option D confuses accountability with responsibility; accountability remains with the executive even when assurance activities are delegated.
Community Discussion
No community discussion yet for this question.