Question
What is the minimum number of management stages required by PRINCE2?
Options
- ATwo stages: to initiate and to deliver the project
- BOne stage: to cover the whole project
- CThree stages: to initiate, to deliver and to close the project
- DFour stages: to start, to initiate, to deliver and to close the project