What is the minimum number of management stages required by PRINCE2?

The correct answer is A. Two stages: to initiate and to deliver the project. See the full explanation below for the reasoning.

Question

What is the minimum number of management stages required by PRINCE2?

Options

  • ATwo stages: to initiate and to deliver the project
  • BOne stage: to cover the whole project
  • CThree stages: to initiate, to deliver and to close the project
  • DFour stages: to start, to initiate, to deliver and to close the project

How the community answered

(43 responses)
  • A
    84% (36)
  • B
    5% (2)
  • C
    9% (4)
  • D
    2% (1)

Community Discussion

No community discussion yet for this question.