What is the minimum number of management stages required by PRINCE2?
The correct answer is A. Two stages: to initiate and to deliver the project. See the full explanation below for the reasoning.
Question
What is the minimum number of management stages required by PRINCE2?
Options
- ATwo stages: to initiate and to deliver the project
- BOne stage: to cover the whole project
- CThree stages: to initiate, to deliver and to close the project
- DFour stages: to start, to initiate, to deliver and to close the project
How the community answered
(43 responses)- A84% (36)
- B5% (2)
- C9% (4)
- D2% (1)