PRINCE2-FOUNDATION · Question #999

PRINCE2-FOUNDATION Question #999: Real Exam Question with Answer & Explanation

The correct answer is A. Two stages: to initiate and to deliver the project. See the full explanation below for the reasoning.

Question

What is the minimum number of management stages required by PRINCE2?

Options

  • ATwo stages: to initiate and to deliver the project
  • BOne stage: to cover the whole project
  • CThree stages: to initiate, to deliver and to close the project
  • DFour stages: to start, to initiate, to deliver and to close the project