PRINCE2-FOUNDATION · Question #998
PRINCE2-FOUNDATION Question #998: Real Exam Question with Answer & Explanation
The correct answer is A. The project's approach to engaging with its stakeholders must be defined. See the full explanation below for the reasoning.
Question
Which is a minimum requirement for applying the organization theme?
Options
- AThe project's approach to engaging with its stakeholders must be defined
- BRoles must be combined to reduce the number of individuals needed on the project
- CDuring a procurement the senior supplier must be appointed from the customer organization
- DThe project team must change at each end stage of the project life cycle